Solar electricity is the extreme example. Commercially available photovoltaic (PV) systems are in the region of 5 to 19% efficient – and to power the 20 MW electricity demand of mainland St Vincent would require installation of 40 acres of PV panels, at a capital cost of over US$100 million – and the installation would only produce power when the sun is shining!
So despite its massive potential, PV is not yet ready for its large-scale moment – although emerging technologies and manufacturing methods promise to change that, with radical efficiency gains, flexibility in application and plummeting costs. In the meantime though, on a small scale, existing PV technology is entirely feasible. It is perhaps surprising to learn that the countries with the largest amounts of PV capacity installed are not-so-sunny Germany and Japan. Surely then, PV should be more widely used in the Caribbean?
So far, the widely-used renewable energy technology in the region is hydroelectricity, which Dominica and St Vincent have installed. The up-front costs of these installations were significantly higher than the costs would have been for the equivalent amount of diesel power. But the point about renewable energy is that once the capital has been expended to build the plant, the fuel cost is practically zero, while that of a diesel plant can account for up to two thirds of the total operating cost – so the economics work out in favour of the renewable energy investment over the lifetime of the plant.
Add to this the fact that sky-high and increasing oil prices will fuel increasing R&D into renewable technologies, thus driving capital costs down and conversion efficiencies up even further, and we see that technology and economics are not the barriers to the present and future use of renewable energy in the Caribbean.
THE TECHNICAL CONDITIONS
Technically, three fundamental conditions will need to be met for green, self-sustainable electricity in our region of sun, sea and sand. These are:
- A reliable, renewable source of large-scale, constant (baseload) power;
- A mix of medium and small-scale renewable sources, allied with energy efficiency and conservation measures, and
- Interconnection of some of the OECS power grids.
The critical condition is the first, and to find the source that can satisfy it, look to the sand. The black sands found on some of our islands give away their volcanic heritage – and indicate the potential for the widespread use of geothermal energy (literally, heat from the earth) to produce a large, constant and renewable baseload electricity supply to the region.
A geothermal energy project now being implemented on Nevis is at the vanguard of this idea. The Nevis project is reported to have proven the feasibility of installation, at a single geothermal site, of a 34 MegaWatt (MW) geothermal plant, construction of which is scheduled to commence by October 2008. If this capacity is implemented, it will be sufficient to supply all of Nevis – and St Kitts, via submarine transmission cable – with baseload power. The project developer is now investigating two other sites to determine the total geothermal resource on Nevis, which at this point the developer estimates to be in the region of 200 – 500 MW.
Then consider that agreements for geothermal investigations have recently been announced by two other OECS countries, and that the aggregate peak demand for electricity in the OECS countries is now about 250 MW, and we see that the available geothermal resource in the OECS could outnumber today’s power demand by several times.
The basic purpose of the second condition is to provide capacity to cover growth in electricity demand over the interim period, but without making significant new investments in diesel plant. To satisfy this condition, add wind and sun. In practical terms in this regard, OECS governments and power companies should do 3 things:
- Invest in wind power generated by refurbished wind turbines that will be easier and less costly to install on small islands and will have an economic life of about 15 years (coinciding with when the grid bringing the baseload geothermal power has come on stream);
- Develop and implement legislation to encourage the installation of grid-connected solar photovoltaics (PV) and wind systems by private customers. This legislation must include a) suitable tariff arrangements between the utilities and the individual power producers, and b) removal of import tariffs on renewable energy equipment and materials, to allow the market to develop;
- Implement energy efficiency and demand-side management programs to reduce overall national energy consumption per unit of output.
Governments in the region have already progressed on the last of these items, with the implementation of the admirable Cuban-sponsored program for the replacement of incandescent bulbs with energy-efficient bulbs.
The first two listed conditions for achieving the overall goal of OECS electricity self-sufficiency are necessary, but not sufficient. Because some of the OECS islands will not have geothermal potential, interconnection of some of the power grids will be required between the geothermal haves and the have-nots. At first glance, a system comprising an interconnected northern OECS grid, a southern OECS grid and Dominica separate in the middle, could be one possible configuration.
Though it will be a large and costly undertaking, the main barriers to establishing such a grid are not technical. Undersea high-voltage power transmission is a well-established practice; such grids exist in various parts of the world (the first in the region was the 23-mile link commissioned in 1966 between Trinidad and Tobago) and more are being planned – some specifically to transmit wind power from remote or offshore locations to load centers.
An OECS interconnection project will be more ambitious than most and will have its fair share of specific challenges (such as deep waters in some areas and the relatively large number of interconnected countries). But the technical problems can be solved, given the right set of conditions – and these conditions are mostly in the realm of policy.
Next: The Policy Problem  Article section: 1 2 3 |